Kondinin Energy works with Ballardong Aboriginal Corporation (BAC) and Ballardong representatives to understand and protect Aboriginal cultural heritage and maintain respectful, ongoing engagement.
A Noongar Standard Heritage Agreement was signed with BAC in November 2023. This provides the framework for heritage engagement, including proposed works notices, survey processes and cultural protocols.
Aboriginal heritage due diligence was completed in 2023. Archaeological and ethnographic surveys followed in March 2024, involving Ballardong Cultural Heritage Officers and Traditional Owners nominated by the Ballardong Cultural Advice Committee, supported by independent heritage specialists Archae-Aus.
The surveys helped identify cultural heritage values that needed to be protected. Ballardong input informed changes to the project layout, including the relocation of two wind turbines and associated access tracks to avoid culturally significant areas.
Heritage protection remains part of construction planning. The project is working with BAC on monitoring arrangements for initial ground-disturbing works, cultural heritage inductions and procedures for responding if previously unidentified heritage is encountered.
These arrangements build on the survey findings, agreed heritage exclusion areas and Ballardong cultural protocols. Heritage information will be managed respectfully, with public information agreed with the appropriate Ballardong representatives.
Engagement with BAC will continue through construction and operations. The project is progressing an Indigenous Relationship Agreement with BAC to support long-term engagement and agreed cultural heritage, employment, training, supplier participation and benefit-sharing outcomes.
To ask about the project’s cultural heritage engagement, contact [email protected].